Four projects now touch Monroe Drive along Morningside's western edge. Only one has broken ground and has a budget and a finish date. The Monroe Drive Safe Streets Project broke ground in July and is scheduled to wrap in July 2028. It was designed around current and forecast traffic, and the city has put the impact of larger future developments on the developers who build them. Amsterdam Walk, the planned Piedmont Park entrance at Piedmont Avenue, and the next BeltLine segment north of Ansley Mall will each arrive on their own schedules. Those schedules are much less certain than the road's.
The One Project With a Finish Date
The Atlanta Department of Transportation broke ground on the Monroe Drive Safe Streets Project on July 22, 2026. The project will reduce Monroe from four travel lanes to three between Armour Drive and 8th Street, with one lane in each direction and a center turn lane. ATLDOT's project page lists the budget at $18,448,979.97, with construction starting July 15, 2026 and finishing July 3, 2028. The city says the three-lane design is meant to slow drivers down and cut crashes by as much as 30%.
The work comes in two phases. That matters for anyone who uses Monroe to get to Ansley Mall or Piedmont Park. ATLDOT's April 14, 2026 project FAQ lays out the sequence:
- Phase I runs from just north of Park Drive up to Armour Drive, on a tentative 12-month schedule. Counting from the July start, that points to roughly summer 2027.
- Phase II covers 8th Street through Park Drive, including the roundabout and minor improvements at the Montgomery Ferry Road intersection. It is expected to take 12 to 18 months.
- Both phases together are expected to take 24 to 30 months, which lines up with the city's July 2028 finish date.
The finished street will have marked crosswalks at 29 locations, two new pedestrian hybrid beacons and six new rapid-flashing beacons. Bulb-outs, refuge islands and sidewalk and ADA ramp replacements are planned where needed. At Montgomery Ferry, the plan adds upgraded ramps and crosswalks, a raised median, and up to four feet of extra pavement on the northbound side to ease the turn. At Piedmont Avenue, new curb lines and ramps will shorten pedestrian crossings. Full signals stay at Amsterdam Avenue, Virginia Avenue, Worchester Drive, Dutch Valley Road, the Ansley Mall driveway and Montgomery Ferry.
The project won't add bike lanes. A 2024 review looked at unprotected lanes as narrow as 3.5 feet, which would have needed design variances, and those variances weren't approved. The design adds safe bike crossings at the BeltLine and 10th Street intersection and at Park Drive.
For daily routes, the city hasn't published a fixed closure map. The FAQ says city staff will review each contractor request for lane closures and detours, and that traffic advisories will go out before disruptions.
Built Around Today's Traffic, by Design
In the FAQ, residents asked whether the plan accounted for the traffic study prepared for Amsterdam Walk. The city's written answer says any improvements recommended in the Amsterdam Walk development documents "will be the responsibility of the developer," and that the project's scope doesn't stand in the way of those future upgrades. On future developments more broadly, the city said the final scope approved in 2021 covers existing and forecast conditions. Developments not included in that forecast would have to offset their own impacts on Monroe.
So the street now under construction is sized for the corridor as the city studied it, and anything larger built along it brings its own traffic obligations. This explains why opinions at the groundbreaking split the way they did. Both sides were reported side by side:
"Monroe Drive, from all the statistics some of us have seen, it's just about at that threshold where it's no longer viable to reduce the lanes down." Charlie Kaften, president of the Yorkshire Townhomes Homeowners Association (quoted by Rough Draft Atlanta)
"We truly are sorry if these changes make some commutes longer or create additional congestion. That's a real concern, and we don't dismiss it. But Atlanta is a Vision Zero city because we believe safety has to come first." Thomas Hyneman, co-founder of Atlanta Families for Safe Streets
Kaften also said neighbors are concerned that side streets could become cut-throughs. District 6 Councilmember Alex Wan pointed to the people struck along the corridor.
Amsterdam Walk Has Approvals but No Construction Date
The largest of those future developments sits at Monroe and Amsterdam. City Council approved the scaled-back rezoning 8–6 in April 2025. On September 17, 2026, the Invest Atlanta board voted 6–2 to approve a property tax break of nearly $15 million for the project from Portman Holdings. As it stands, the multi-phase plan includes 1,100 rental units, 1,435 parking spaces and 150,000 square feet of commercial space on 11 acres, with 39 affordable units. Council member Matt Westmoreland and Atlanta school board member Ken Zeff voted no. Zeff raised concerns about the share of the incentive that would come from Atlanta Public Schools.
Phase one, as filed in May, calls for 666 apartments and 96,452 square feet of commercial space in five connected buildings that top out at 85 or 95 feet. Two of the buildings wrap parking garages. Portman filed a Special Administrative Permit application that month as a first step. Reporting hasn't said whether it has been approved. In May, Invest Atlanta projected that the residential component would take two years to build and open in 2028. That was a forecast. No construction start has been confirmed.
Amsterdam Walk has been a shopping center with restaurants, family activities and small businesses for nearly 30 years. The plan would replace most, if not all, of the existing buildings. The May coverage names Red Light Café among the longtime businesses there but doesn't say when individual tenants would leave. If Portman's two-year build starts soon, it would run alongside the road work through July 2028. Neighbors raised that possible overlap at the groundbreaking.
The Park Corner and the Trail Are on Longer Schedules
The other two changes are farther out still. Both depend on purchases or contracts that haven't been finalized.
At Piedmont Avenue and Monroe, the Piedmont Park Conservancy is buying three parcels to create a new park entrance: a gas station and buildings that include Varuni Napoli and Octopus Kitchen. President and CEO Doug Widener announced the plan at the Conservancy's April luncheon, as part of a 10-year master plan that would extend the Commons out to that corner. The April announcement didn't give a closing date for either restaurant or a construction schedule for the entrance. The Conservancy's plan site describes a 10-to-15-year horizon for the full plan. For now, the corner is as it was.
North of Ansley Mall, BeltLine Northeast Trail Segment 3 has slipped. In its June 2026 update, published July 9, Atlanta BeltLine Inc. expected construction to mobilize this summer and estimated 42 months of work. ABI's September 11 update moved bid pricing to October 2026. It now expects to issue a notice to proceed by year's end and start construction in early 2027, with about 36 months of work. ABI calls it one of its largest projects. ABI hasn't published an opening date. A 36-month build starting in early 2027 would run to about early 2030. The project includes connectors to MARTA Lindbergh Center, PATH400 and the Armour-Ottley district, plus truss bridges over Peachtree Creek and the freight rail lines.
So the trail still ends at Mayson Street. Segment 2 covers the 1.2 miles from Westminster Drive to Mayson Street and Plasters Avenue, with access at Piedmont Park's North Woods, Westminster, Piedmont Avenue, Ansley Mall and Montgomery Ferry Road. The changes at Ansley Mall are already open. Selig Enterprises' pedestrian bridge and Lewis Barbecue opened in December 2025, connecting the mall to the trail at 1544 Piedmont Avenue.
The Calendar as It Stands
Here's the corridor's timeline in order, starting with dates already on this month's calendar:
- Thursday, October 8, 6:15–8 p.m. The free Atlanta Beltline Thursday Run Club meets at Lewis BBQ, with 2- and 4-mile options.
- Friday, October 9, 8:30–10:30 a.m. Trees Atlanta holds a plant-care volunteer shift at the BeltLine gate behind the Ansley Mall Publix.
- October 17 and October 31, 9 a.m.–1 p.m. Piedmont Park's Green Market.
- October 2026. Bid pricing is due for BeltLine Segment 3.
- End of 2026. ABI expects to issue Segment 3's notice to proceed.
- Early 2027. Segment 3 construction is expected to begin.
- Around summer 2027. Monroe Phase I, from Park Drive to Armour, is due based on its 12-month estimate. Phase II is expected to follow right after.
- 2028. Invest Atlanta's May forecast for Amsterdam Walk's first residential phase. It hasn't been confirmed.
- July 3, 2028. ATLDOT's listed finish date for the Monroe Drive project.
- No date given in the April announcement. The Piedmont Avenue park entrance and what happens to Varuni Napoli and Octopus Kitchen.
If you're weighing how these projects might affect a home near Monroe, from the Amsterdam side to the Montgomery Ferry end, the Allie Burks Group follows each of these schedules as they change. Schedule a Private Consultation, and we'll go through what's confirmed and what's still pending for your street.